RAY BROOK, NY – Adirondack Park Agency Status Update on Cellular Projects in the Adirondack Park.
Status report for cellular carrier projects approved, currently under review or projects submitted but deemed incomplete.
This status update covers only cellular carrier projects and does not include other previously reported telecommunication projects (e.g., radio, television, emergency services, etc.).
At the May 2008 Park Agency meeting the Board approved one cellular carrier permit for a new Verizon freestanding tower. This tower is located along US Route 9 in the town of Schroon, Essex County between exits 28 and 29 of the Adirondack Northway.
At the April 2008 Park Agency meeting the Board approved a second renewal request for the Nextel temporary tower located in the Town of Mayfield, Fulton County.
Cellular carrier activity since January 1, 2008:
•3 cellular carrier permits approved for new towers
• 1 cellular carrier permit approved for co-location
• 1 cellular carrier application for a new tower remains incomplete
• 1 cellular carrier application for upgrades to an existing tower remains incomplete
• 0 cellular carrier applications submitted for temporary towers for I-87
Cellular carrier activity May 1973 through present:
• 55 new cellular carrier permits approved authorizing:
o 10 new free standing towers
o 19 co-locations on free standing existing towers
o 6 co-locations on existing buildings
o 5 co-locations on water tanks
o 3 co-locations on existing fire towers
o 2 co-locations on Olympic ski jump
o 2 co-location on smokestack
o 12 tower and/or antenna replacements
o 1 temporary tower and a second renewal (Town of Mayfield, Fulton County)
• 19 cellular carrier permit amendments issued authorizing:
o 10 co-locations on free standing existing towers
o 2 co-location on fire tower
o 1 co-location on existing building
o 1 co-location on Olympic ski jump
o 8 tower and/or antenna replacements
The number of activities approved exceeds the number of permits/amendments issued because some permits/amendments authorized multiple towers or activities in more than one location.